Analysing costs for 2012, it can be observed that the heavier costs, in the whole of costs ([BCI] [ECI]), correspond to “direct costs of network-oriented activities”, and that, among them, the most significant costs are those related to “specific telecommunication equipment/networks”, representing [BCI] [ECI] of total costs.
COSTS |
2012 |
Percentage of total costs |
TOTAL COSTS |
|
|
Total direct and joint costs |
|
|
Total direct costs |
|
|
Direct costs of products and services |
|
|
Direct costs of customer-oriented activities |
|
|
Direct costs of network-oriented activities |
|
|
Specific telecommunication equipment/networks |
|
|
Others |
|
|
Total joint costs |
|
|
Joint cost of customer-oriented activities |
|
|
Joint cost of network-oriented activities |
|
|
Total common costs |
|
|
Values in Euros
[ECI]
Breaking down costs related to “specific telecommunication equipment/networks”, it is observed that the main component of these costs concerns DTT equipment (vide Table 21) which represent around [BCI] [ECI] of total costs, the second most relevant item being staff costs (with a weight by [BCI] [ECI] of total costs).
COSTS |
2012 |
Percentage of costs |
Specific telecommunication equipment/networks |
|
|
Broadcasting equipment - DTT |
|
|
Staff costs |
|
|
Others1 |
|
|
Values in Euros
[ECI]
A broken-down analysis of costs related to the “Broadcasting equipment - DTT” item shows that costs with transmitters are the heaviest ([BCI] [ECI]), followed by costs with electricity infrastructures ([BCI] [ECI]).
COSTS |
2012 |
Percentage of costs |
Broadcasting equipment - DTT |
|
|
Transmitters |
|
|
Electricity infrastructures |
|
|
Others |
|
|
Values in Euros
[ECI]
As regards staff costs associated to specific telecommunication equipment/networks (which have a significant weight in the scope of direct costs related to “specific telecommunication equipment/networks”), it is not possible to replicate the amount of [BCI] [ECI] Euros entered in the CAS with detailed data submitted by MEO, having been obtained a cost, 14% higher than the preceding one, amounting to [BCI] [ECI] Euros, on the basis of detailed information on staff costs, and taking into account staff costs associated to the description “Broadcasting equipment - DTT”.
1 Concerning (i) radiating systems, (ii) containers, (iii) HVAC systems; (iv) SDH-ASI converters, (v) change in frequencies, (vi) head-end, (vii) technical design, (viii) towers, (ix) transmission system, (x) others, (xi) management network and (xii) civil engineering infrastructures, where each represents less than 10% of costs.