Maximum prices for call origination and termination services in 2010


PTC’s proposalhttps://www.anacom.pt/render.jsp?contentId=55129
 

Maximum prices set by ICP-ANACOMhttps://www.anacom.pt/render.jsp?contentId=55130


PTC’s proposal

Call origination and termination prices proposed by PTC to apply in RIO 2010 (as from 01.01.2010) are shown on the table below.

Table 9 – Call origination and termination prices proposed by PTC to apply in RIO 2010

Level

Call activation

Price per minute

Peak hours

Off-peak hours

Local

0,50

0,42

0,23

Simple Tandem

0,50

0,55

0,31

Double Tandem

0,50

0,68

0,39

Figures in Euro cents (VAT excluded). Charge by the second from the first second.
Peak hours: 9a.m.-7 p.m.; Off-peak hours: 7 p.m.-9 a.m.

According to PTC, the fundamental features of this proposal are:

(i) Maintaining the same prices for call origination and termination services;
(ii) Establishing a single call activation price, regardless of the interconnection level, which is slightly higher than the price currently applied for local level;
(iii) Cost-orientation for all interconnection levels.

The following table shows specific variations, for each tariff element, of the proposal presented by PTC in regards to the tariff scheme currently in force, being apparent that PTC’s proposal increases the local level call activation price and price per minute, as well as the simple tandem off-peak price per minute, reducing all other elements.

Table 10 – Variation of elements of the tariff proposed by PTC for 2010 in regards to the tariff scheme currently in force

Level

Call activation

Price per minute

Peak hours

Off-peak hours

Local

2,0%

10,5%

21,1%

Simple Tandem

-3,8%

-5,2%

6,9%

Double Tandem

-19,4%

-31,3%

-26,4%

Source: PTC.

In average, and considering the traffic structure foreseen for 2010, ICP - ANACOM’s  estimates lead to the conclusion that the tariff scheme proposed by PTC entails a revenue reduction of [SCI] [ECI] in the call origination service and a revenue increase in the call termination service of [SCI] [ECI], which results in an overall average increase of around 2%. This increase arises specifically from the local level ([SCI] [ECI]), whereas revenues of simple tandem and double tandem levels would decrease [SCI] [ECI] and [SCI] [ECI] respectively 1.

Table 11 – Variation of average revenues resulting from the tariff scheme proposed by PTC for 2010 in regards to average revenues resulting from the tariff scheme currently in force [SCI]

Level

Termination

Origination

Weighted Interconnection Total

Peak

Off-peak

Average

Peak

Off-peak

Average

Local

Simple Tandem

Double Tandem

Average

[ECI] Source: ICP-ANACOM estimates

Given revenues indicated on the preceding table and direct and joint unit costs estimated by ICP - ANACOM, it was calculated that PTC’s overall margin in regards to direct and joint costs for 2010, resulting from PTC’s tariff scheme proposed for 2010, would be around 22% (see table below).

Table 12 - Estimated margins for 2010, resulting from PTC’s tariff scheme proposed for 2010 [SCI]

 

Margins considering direct + joint costs

Traffic (million

minutes)

Estimated cost

(thousands of

Euros)

Estimated

revenue

(thousands of

Euros)

Estimated

margin

(thousands of

Euros)

Margin (%

Estimated cost)

Termination

 

 

 

 

17%

Origination

 

 

 

 

32%

Total

 

 

 

 

22%

[FIC] Source: ICP-ANACOM estimates

In case total cost estimates were considered (direct, joint and common costs – assuming they represent a maximum of 10% of remaining costs), a global margin of approximately 11% would result from applying PTC’s tariff scheme proposed for 2010, as shown on the following table.

Table 13 - Estimated margins for 2010, resulting from PTC’s tariff scheme proposed for 2010, considering total cost estimates [SCI]

 

Margins considering total costs (with common unit costs = 10% of total direct

and joint costs)

Traffic (million

minutes)

Estimated cost

(thousands of

Euros)

Estimated

revenue

(thousands of

Euros)

Estimated

margin

(thousands of

Euros)

Margin (%

Estimated cost)

Termination

 

 

 

 

7%

Origination

 

 

 

 

20%

Total

 

 

 

 

11%

[FIC] Source: ICP-ANACOM estimates

In summary, it must be taken into account that:

(i) Prices put forward in PTC’s proposal represent an increase of the local level margin, which is not consistent with the necessary incentive to the development of interconnection network infrastructures;

(ii) In case total costs estimated by ICP-ANACOM were considered (direct, joint and common costs – assuming they represent a maximum of 10% of remaining costs), a global margin of approximately 11% would result from applying PTC’s tariff scheme proposed for 2010, which fails to comply with the obligation of cost orientation of prices that falls on PTC.

It follows from all the foregoing that ICP-ANACOM deems PTC’s proposal to be unacceptable.

Maximum prices set by ICP-ANACOM

Maximum prices presented below took several elements into consideration, namely keeping the balance between the need to promote incentives for the development of an independent infrastructure, the promotion of effective competition, the need for interconnection prices to reflect the way interconnection costs occur, regardless of PTC’s management policies, and the need to improve the position of prices in PTC’s reference proposal within the European context.

As regarding common costs, it is considered, as referred earlier, that the overall margin encapsulated in maximum prices must be sufficient to recover common costs of an efficient operator resulting from a situation of competition, in line with EC’s understanding on an appropriate approach for the establishment of interconnection prices, which supports the use of long-term forward-looking incremental costs, not excluding, however, the use of justified margins as means to recover costs.

It is also considered that maximum prices should allow the downward trend of the interconnection price margin in regards to direct and joint costs to continue, as has been the case in previous years (except for results for 2008, which reported a more significant cost decrease that estimated - see graph below), with no increases of margins associated to any traffic levels (local, simple tandem, double tandem).

Graph 4 - Evolution of the deviation of PTC’s total direct and joint costs from revenues

It is also considered that maximum prices should allow the downward trend of the interconnection price margin in regards to direct and joint costs to continue, as has been the case in previous years (except for results for 2008, which reported a more significant cost decrease that estimated - see graph below), with no increases of margins associated to any traffic levels (local, simple tandem, double tandem).
(Click to enlarge image)

Accordingly, it is deemed that maximum interconnection prices to prevail in RIO 2010 as from 15.04.2010, are as follows:

Table 14 – Interconnection prices defined by ICP-ANACOM to apply in RIO 2010 for origination and termination services

Level

Call activation

Price per minute

Peak hours

Off-peak hours

Local

0,48

0,38

0,19

Simple Tandem

0,48

0,51

0,26

Double Tandem

0,48

0,62

0,33

Figures in Euro cents (VAT excluded). Charge by the second from the first second.
Peak hours: 9a.m.-7 p.m.; Off-peak hours: 7 p.m.-9 a.m.

These maximum prices entail, in regards to RIO 2009 prices currently in force, approximate average nominal reductions (based on a three-minute call and considering PTC’s forecast traffic profile for 2010) by 5.3% for call termination and by 10.0% for call origination, which corresponds to actual average reductions by 4.5% and 9.2% respectively, taking into account the expected inflation in the State’s Budget for 2010 2. As there seems to be no reason to impose a different activation price according to the interconnection level, PTC’s proposal for harmonization is accepted, and thus maximum prices defined by ICP - ANACOM, as presented, reflect such option.

The following table represents the estimated variation of maximum prices defined to apply in RIO 2010 in regards to RIO 2009 prices currently in force, for a three-minute call.

Table 15. Variation of ICP-ANACOM’s interconnection prices for RIO 2010, for origination and termination services, based on a three-minute call, in regards to RIO 2009 (in force in December 2009)

 

Termination

Origination

Weighted Interconnection Total

Peak

Off-peak

Average

Peak

Off-peak

Average

Local

-0,6%

-0,9%

-0,7%

-0,6%

-0,9%

-0,7%

-0,7%

Simple Tandem

-11,1%

-9,4%

-10,6%

-11,1%

-9,4%

-10,8%

-10,7%

Double Tandem

-34,8%

-33,5%

-34,5%

-34,8%

-33,5%

-34,6%

-34,6%

Average

-5,5%

-4,8%

-5,3%

-10,1%

-4,8%

-10,0%

-6,7%

Source: ICP-ANACOM calculations.

In case traffic profiles estimated by PTC for 2010 were considered, namely as regards call average duration, the average variation of revenues resulting from maximum prices in regards to RIO 2009 prices, which is very close to the variation calculated  for a three-minute call, would be as follows:

Table 16 - Variation of interconnection revenues resulting from maximum prices defined to apply in RIO 2010, for origination and termination services, based on a three-minute call, in regards to RIO 2009 (in force in December 2009)

 

Termination

Origination

Weighted Interconnection Total

Peak

Off-peak

Average

Peak

Off-peak

Average

Local

-0,7%

-0,7%

-0,7%

-0,7%

-0,9%

-0,7%

-0,7%

Simple Tandem

-10,8%

-9,4%

-10,5%

-10,8%

-9,0%

-10,5%

-10,5%

Double Tandem

-33,9%

-34,4%

-34,0%

-34,5%

-31,8%

-34,0%

-34,0%

Average

-6,0%

-4,1%

-5,5%

-9,9%

-9,4%

-9,8%

-6,9%

Source: ICP-ANACOM calculations

Based on estimates of direct and joint unit costs shown earlier, it is estimated that the deviation of total direct and joint costs from revenues resulting for the RIO 2010 tariff scheme will bring about an overall margin of 11% for all interconnection services, as shown in the table below.

Table 17 – Estimated deviation for 2010 of total direct and joint costs from revenues, resulting from applying the RIO 2010 tariff scheme defined by ICP-ANACOM, with ICP-ANACOM’s cost estimates and PTC’s traffic volume estimates [SCI]

 

Margins considering direct + joint costs

Traffic (million

minutes)

Estimated cost

(thousands of

Euros)

Estimated

revenue

(thousands of

Euros)

Estimated

margin

(thousands of

Euros)

Margin (%

Estimated cost)

Termination

 

 

 

 

7%

Origination

 

 

 

 

22%

Total

 

 

 

 

11%

[ECI] ICP-ANACOM calculations

In case total costs estimates were considered (direct, joint and common costs – assuming they represent a maximum of 10% of remaining costs), a global margin of approximately 1%, would result from applying maximum prices defined by ICP - ANACOM,  as shown on the following table.

Table 18 - Estimated margins for  2010, resulting from the RIO 2010 tariff scheme defined by ICP - ANACOM, considering estimates of total costs  [SCI]

 

Margins considering total costs (with common unit costs = 10% of total direct

and joint costs)

Traffic (million

minutes)

Estimated cost

(thousands of

Euros)

Estimated

revenue

(thousands of

Euros)

Estimated

margin

(thousands of

Euros)

Margin (%

Estimated cost)

Termination

 

 

 

 

-3%

Origination

 

 

 

 

11%

Total

 

 

 

 

1%

[ECI] ICP-ANACOM estimates

Maximum prices thus defined allow the margin downward trend to continue, as has been the case in the past, specifically for each interconnection level (as shown in the table below), margins for direct and joint costs converging to figures close to 10% for all interconnection levels.

Table 19 - Evolution of estimated deviations, from direct and joint costs estimated by ICP-ANACOM, of revenues that result from applying the RIO 2009 tariff scheme (in force in December 2009) in 2010, and those resulting from the RIO 2010 tariff scheme defined by ICP - ANACOM

 

Estimates for 2010 based on RIO 2009 (in force in December 2009)

Estimates for 2010 based on the 2010 tariff scheme defined by ICP - ANACOM

Termination

Origination

Interconnection Total

Termination

Origination

Interconnection Total

Local

7%

30%

11,1%

6%

29%

10,4%

Simple Tandem

20%

32%

25,1%

7%

18%

12,0%

Double Tandem

77%

68%

72,2%

17%

11%

13,7%

Source: ICP-ANACOM calculations

Without prejudice, in average annual terms, figures of average price and margin variations in regards to direct and joint unit costs differ from those shown above, given that the date of entry into force of the tariff scheme defined by ICP - ANACOM is 15.04.2010, thus average prices in force for 2010 result from striking a balance, in terms of days in which each tariff scheme is in force, between the RIO 2009 tariff scheme and the one defined herein by ICP - ANACOM.

Accordingly, if traffic profiles estimated by PTC for 2010 were considered, namely as regards the average call duration, the average variation of revenues resulting from maximum prices in regards to RIO 2009 prices, and the date of entry into force being 15.04.2010, would be as follows. Note that if a three-minute call was considered, the average variation would be -4.9%.

Table 20 - Variation of interconnection revenues resulting from maximum prices defined to apply in RIO 2010 as from 15/04/10, for origination and termination services, based on an average duration call, in regards to RIO 2009 (in force in December 2009)

 

Termination

Origination

Weighted Interconnection Total

Peak

Off-peak

Average

Peak

Off-peak

Average

Local

-0,7%

-0,7%

-0,7%

-0,7%

-0,9%

-0,7%

-0,7%

Simple Tandem

-7,8%

-6,5%

-7,5%

-7,8%

-6,3%

-7,6%

-7,5%

Double Tandem

-23,9%

-24,1%

-23,9%

-24,3%

-22,4%

-23,9%

-23,9%

Average

-4,4%

-3,0%

-4,0%

-7,1%

-6,7%

-7,1%

-5,0%

Source: ICP-ANACOM calculations

Consistently with estimates of direct and joint unit costs shown earlier, it is estimated that the deviation of total direct and joint costs from revenues estimated for 2010, resulting from the two different tariffs in force this year, brings about an overall margin of 13% for all interconnection services, as shown in the table and graph below, which also allows the margin downward trend to continue, as in the past, and to converge to figures close to 10%.

Table 21 - Estimated deviation for 2010, of total direct and joint costs from revenues resulting from applying the RIO 2010 tariff scheme defined by ICP-ANACOM, with ICP-ANACOM’s cost estimates and PTC’s traffic volume estimates [SCI]

 

Margins considering direct + joint costs

Traffic (millions of minutes)

Estimated cost (thousands of Euros)

Estimated revenue (thousands of Euros)

Estimated margin (thousands of Euros)

Margin (% estimated cost)

Termination

 

 

 

 

9%

Origination

 

 

 

 

25%

Total

 

 

 

 

13%

[ECI] Source: ICP-ANACOM calculations

Graph 5 - Evolution of the deviation of PTC’s total direct and joint costs from revenues

Consistently with estimates of direct and joint unit costs shown earlier, it is estimated that the deviation of total direct and joint costs from revenues estimated for 2010, resulting from the two different tariffs in force this year, brings about an overall margin of 13% for all interconnection services, as shown in the table and graph below, which also allows the margin downward trend to continue, as in the past, and to converge to figures close to 10%.
(Click to enlarge image)

In case total cost estimates were considered (direct, joint and common costs – assuming they represent a maximum of 10% of direct and joint costs), a global margin of approximately 3% would result from applying both tariff schemes during 2010, as shown on the following table.

Table 22 - Estimated margins for 2010, resulting from applying both tariff schemes during 2010 , considering estimates of total costs [SCI]

 

Margins considering total costs (with common unit costs = 10% of total direct

and joint costs)

Traffic (millions of minutes)

Estimated cost (thousands of Euros)

Estimated revenue (thousands of Euros)

Estimated margin (thousands of Euros)

Margin (% estimated cost)

Termination

 

 

 

 

-1%

Origination

 

 

 

 

14%

Total

 

 

 

 

3%

[ECI] ICP-ANACOM estimates

Average 2010 prices thus estimated also allow the margin downward trend, in regards to direct and joint costs, to continue, as has been the case in the past, specifically for each interconnection level, as shown in the table below.

Table 23 – Margins associated to RIO 2009 prices compared to those resulting from maximum prices now defined by ICP-ANACOM 3

 

Estimates for 2010 based on RIO 2009 (in force in December 2009)

Estimates for 2010 based on the 2010 tariff scheme defined by ICP - ANACOM

Termination

Origination

Interconnection Total

Termination

Origination

Interconnection Total

Local

7%

30%

11,1%

6%

29%

10,4%

Simple Tandem

20%

32%

25,1%

11%

22%

15,7%

Double Tandem

77%

68%

72,2%

35%

28%

31,0%

Source: ICP-ANACOM calculations

It is thus understood that these maximum prices make it possible to keep the balance between the need to promote incentives to the development of an independent infrastructure and the promotion of an effective competition, maintaining a favourable position regarding current European practices on this matter (as shown on this document’s following section), whilst maintaining common costs at the level referred above to be reasonable.

Notes
nt_title
 
1 PTC refers that the presented proposal shows a variation of [SCI] [ECI] of average revenues. Without prejudice, estimates performed by ICP - ANACOM, based on traffic profiles also indicated by PTC, do not replicate this figure, and on the contrary, it is estimated that PTC’s proposal represents an increase by [SCI] [ECI] of the average revenue.
2 The State Budget for 2010 provides for an inflation value of 0.8%.
3 Estimated deviations, from direct and joint costs estimated by ICP-ANACOM, of revenues that result from applying the RIO 2009 tariff scheme (in force in December 2009) in 2010, and those resulting from applying average prices for 2010 (which result from applying the RIO 2010 tariff scheme defined by ICP - ANACOM to prevail as from 15.04.2010).